November 5, 2026
"I think we found utilities that no one knew existed. It's very complex," Oakland transportation director Josh Rowan said at the October 21 ribbon-cutting for the new protected bikeway between Lake Merritt and the 19th Street BART station, as The Oaklandside reported. He was talking about three blocks of 20th Street. About a mile away, Lakeshore Avenue's crews had run into much the same thing.
Each project was slowed by what turned up once crews dug into the roadbed. Each of the lake's other planned segments is also tied to a repaving job that will open the street and expose whatever is under it. If you walk, run, ride or drive the lake regularly, that link explains the delays so far. It also explains the dates you should expect for the rest of the loop.
The new route is officially the 19th Street BART to Lake Merritt Urban Greenway. It runs along 20th Street, also called Thomas L. Berkley Way. Along with the protected bike lanes, it added pedestrian crossings, LED street lights and traffic signal upgrades. The signal work meant laying fiber optic cable under the road. Rowan said that messy cabling and buried infrastructure along the route held up the build.
The design is unusual for Oakland. In places the bikeway sits at sidewalk height, with a wide asphalt strip around it. City planners call this "at-grade." Rowan called it his preference: "Big wide sidewalk, at-grade path. It's very pleasant." To make room, the city removed a driving lane.
The project took a long time. Robert Prinz of Bike East Bay said at the ceremony that his group first sent letters of support for a protected lane on this road a decade ago. Part of the funding came from state Active Transportation money approved in 2016. BART director Victor Flores noted that the route serves hundreds of BART employees who work at the agency's headquarters at 2150 Webster Street. District 2 council member Charlene Wang described it as one piece of a larger plan: "We are really creating a connected network."
That network is what most lake users are waiting on. Its most-used piece is still fenced off.
The Lakeshore Avenue Separated Bike Lanes Project will put a two-way bikeway on the lake side of Lakeshore between E. 18th Street and El Embarcadero. A physical barrier will separate it from traffic, and a row of parked cars will add a second buffer. The completion date has moved each time the city has updated its project page:
| City update | What it said |
|---|---|
| February 2025 | Construction to start late spring 2025, lasting about 8 months |
| July 2025 | Start on July 21, 2025, lasting about 12 to 15 months |
| June 2026 | Major excavation and base repair to resume June 22, 2026, after a redesign |
| October 2026 | Paving in early 2027, completion in spring 2027 |
The Oaklandside reported in June that paving started in early February 2026. It stopped when crews found the road's base layer far more damaged than expected. Further investigation then found shallow utilities in the work area. OakDOT spokesperson Kent Bravo said the city and its designer redesigned parts of the base repair to avoid them. The contractor, Gallagher and Burk, sent a new price and schedule in April and reached an agreement with the city in May.
According to the city's October update, base repair is now complete. Crews are building concrete bulb-outs and pedestrian refuge islands. The update also says the team is still dealing with "several grading challenges and unforeseen shallow utility conflicts." In the 20th Street case it was utilities "no one knew existed." On Lakeshore the city's phrase is "unforeseen shallow utility conflicts." Both projects hit the same kind of problem.
These bike lanes take longer than paint because each one comes with a road rebuild. The Lakeshore lanes were timed to follow an East Bay Municipal Utility District pipeline replacement that was scheduled to start in October 2024. Lakeshore was already on the city's 5-Year Paving Plan for Fiscal Year 2027. Combining the two let the city build the bikeway two years earlier than the paving plan alone would have. The Oaklandside also reported that the city had at times shared labor costs with PG&E, which wanted to replace its own aging lines under the road.
Pairing the work saves money and avoids tearing up the same street twice. The trade-off is that the bikeway's schedule now depends on the roadbed. A crew can't stripe a bike lane over a base layer that is failing.
One reason the city gives for the lanes is safety, particularly dooring, where a parked car's door swings open into the bike lane. OakDOT has posted signs on Lakeshore telling drivers to check for bikes before opening their doors. Space is the other reason. The mixed-use path beside the street was built in 2009 with Measure DD bond funds. It was meant for pedestrians and slower riders, but it now draws so many people on foot that cyclists often have no room. The new bikeway will give riders their own space away from both cars and walkers.
The city's schedule puts the hardest remaining step, milling and repaving, in the rainy months. The Oaklandside reported that the city's dates depend on weather, since rain usually slows construction. Here's what to expect until then:
Questions about construction go to resident engineer Aaron Mao at [email protected], the contact the city lists on its project page.
The other pieces of the lake loop are set up the same way as Lakeshore. Each comes with repaving, so each will open the road.
| Segment | Where it stands | What's next |
|---|---|---|
| Lakeside Drive / Lake Merritt Boulevard | At the bid-award stage. Plans extend the lake-side two-way bikeway from Madison Street toward 1st Avenue and International Boulevard, with pedestrian and transit improvements | Listed by Oakland's Bicycle and Pedestrian Advisory Committee in October as expected to start construction by spring 2027 |
| Grand Avenue, Broadway to Mandana | Draft detailed design, at 65%, as of the city's Summer 2026 update | Construction expected to begin with repaving in Summer 2027 |
| 1st Avenue / Lakeshore gap, International Blvd to E. 18th St | Design phase | Construction date to be determined |
Grand Avenue will make the biggest difference to the Grand Lake shopping district. The updated design for the stretch from Santa Clara Avenue and Lake Park Avenue to Mandana keeps the front-in angled parking. It adds a separated bikeway protected by parked cars and concrete wheel stops, plus a two-way center turn lane and loading zones. South of Interstate 580, Bike East Bay says Grand goes from four car lanes to three to make room for two-way cycletrack segments that connect to the rest of the loop. The city's project page has a sign-up for updates, and Bike East Bay said community meetings on Grand are coming up this fall.
Lakeside Drive and Grand Avenue will both have their paving opened up, as 20th Street and Lakeshore did. Their published start dates are for when digging begins. The finish dates will depend on what crews find under those streets.
If you're weighing a move near the lake, or wondering how the Grand Avenue work could affect a sale you're planning for 2027, Sallat & Perry Group follows these street projects block by block. Schedule a consultation and we'll walk you through the timing on the streets that matter to you.
Stay up to date on the latest real estate trends.
Whether you’re buying your first home or listing a cherished property, Sallat & Perry Group brings unmatched East Bay insight and a personalized strategy to every transaction.